CA
Tax Tutor
A

Imagine a construction company building a highway overpass — the project spans 3 years, costs crores, and can't be invoiced all at once. That's exactly what Contract Costing is designed to handle: a form of Specific Order Costing used for large, long-duration jobs where each contract is a unique cost centre.

The core challenge in contract costing is profit recognition — how much profit do you show in your books each year, even though the contract isn't finished? The ICAI follows a conservative approach tied to the stage of completion, measured by: Work Certified ÷ Contract Price. Here's the rule: if less than 25% complete, recognise no profit at all (too early to be sure). Between 25–50%, transfer 1/3 of Notional Profit × (Cash Received ÷ Work Certified) to P&L. At 50% or more, use 2/3 of Notional Profit × (Cash Received ÷ Work Certified). Notional Profit = Value of Work Certified − Cost of Work Certified (i.e., total cost to date minus cost of uncertified work).

Two more terms you must know: Retention Money is the amount the contractee (client) withholds until the project is fully complete — it's a security deposit, not yet your cash. Work Uncertified (also called WIP on contract) is work done but not yet approved by the architect/surveyor — it stays on the balance sheet as an asset. If the contract is heading for a foreseeable loss (estimated total cost > contract price), the entire anticipated loss must be charged to P&L immediately — no phasing it out. This comes up frequently in 4-mark and 8-mark questions, often with a partially completed contract and a table to fill.

📊 Worked example

Example 1 — Profit Recognition (≥50% complete)

Rajesh Constructions Ltd. is executing a contract. Details at year-end:

| Item | Amount |

|---|---|

| Contract Price | ₹60,00,000 |

| Cost incurred to date | ₹30,00,000 |

| Work Certified by architect | ₹36,00,000 |

| Work Not Certified (WIP) | ₹2,00,000 |

| Cash received from contractee | ₹28,80,000 |

Step 1 — Stage of Completion

= 36,00,000 ÷ 60,00,000 = 60% → Use the 2/3 formula

Step 2 — Cost of Work Certified

= Total Cost − Uncertified WIP = 30,00,000 − 2,00,000 = ₹28,00,000

Step 3 — Notional Profit

= Work Certified − Cost of Work Certified = 36,00,000 − 28,00,000 = ₹8,00,000

Step 4 — Profit transferred to P&L

= 2/3 × ₹8,00,000 × (₹28,80,000 ÷ ₹36,00,000)

= 2/3 × ₹8,00,000 × 0.80

= 2/3 × ₹6,40,000

= ₹4,26,667

---

Example 2 — Foreseeable Loss

Ms. Iyer's firm has a contract with price ₹40,00,000. Costs to date: ₹20,00,000. Estimated cost to complete: ₹25,00,000.

Estimated Total Cost = 20,00,000 + 25,00,000 = ₹45,00,000

Foreseeable Loss = 40,00,000 − 45,00,000 = ₹(5,00,000)

Transfer the entire ₹5,00,000 loss to P&L immediately. Do not wait for the contract to finish. Answer: ₹5,00,000 charged to P&L this year.

⚠️ Common exam mistakes

  • Forgetting to subtract uncertified WIP before computing Notional Profit. Students use total cost to date directly. Always: Cost of Work Certified = Total Cost − WIP (uncertified work).
  • Applying the wrong fraction. At exactly 50%, use 2/3 — NOT 1/3. The 1/3 fraction applies only when completion is between 25% and below 50%.
  • Ignoring the cash-received ratio. The formulas include a × (Cash Received ÷ Work Certified) adjustment. Students often compute just 2/3 × Notional Profit and stop there — that's wrong unless all certified work is collected.
  • Recognising profit when completion is under 25%. No matter how large the notional profit looks, if the contract is less than 25% done, the profit to P&L is zero. Write it clearly in your answer.
  • Not recognising foreseeable loss in full immediately. Students sometimes try to phase the loss over remaining periods. The rule is: anticipated/foreseeable losses are charged to P&L 100% in the current period — prudence principle applies.
📖 Reference: Contract Costing — Institute of Chartered Accountants of India
Test yourself
Practice questions on this section, AI-graded with citations.
⚡ Practice now →