CA
Tax Tutor
A

Process costing is used in industries where production flows continuously — think paint factories, cement plants, or a dal mill. When units are partially done at the start of a period (called Opening WIP — Work-in-Progress), you need a method to handle their costs fairly. That's where FIFO (First-In, First-Out) comes in: it assumes you finish the old batch first, before starting fresh units.

Here's the core idea: under FIFO, you keep opening WIP costs separate from current period costs. You only use current period costs to calculate the cost per equivalent unit. This is the biggest difference from the Weighted Average Method, where you pool opening WIP costs with current costs. FIFO is more precise — it tells you exactly what it cost this period to produce.

The calculation has four steps. Step 1 — work out Equivalent Units (EU) using the FIFO formula: EU = (Opening WIP units × % work still to be done) + Units started and fully completed this period + (Closing WIP units × % work done). Step 2 — calculate Cost Per Equivalent Unit = Current period costs ÷ Total EU (do NOT add opening WIP costs here). Step 3 — assign costs to completed units: Opening WIP gets its brought-forward cost plus the cost to complete the remaining work; freshly started-and-completed units get the full current cost per EU. Step 4 — value Closing WIP at cost per EU × closing WIP equivalent units.

Why does FIFO matter for exams? The ICAI frequently tests it as a 10–12 mark problem in Paper 4, especially with two or three cost elements (materials, labour, overheads) each at different completion percentages. The examiner loves to give you opening WIP at 40% complete and closing WIP at 60%, forcing you to carefully compute EU for each cost element separately. Always make a neat statement of equivalent units — examiners award step marks.

📊 Worked example

Example 1 — Single cost element

Rajesh Paints Ltd. has the following data for Process 1 in March 2026:

  • Opening WIP: 500 units, 40% complete; cost brought forward ₹18,000
  • Units introduced in March: 4,000
  • Units completed & transferred: 4,200
  • Closing WIP: 300 units, 50% complete
  • Costs incurred in March: ₹1,05,000

Step 1 — Equivalent Units (FIFO)

| Element | Units | % remaining/done | EU |

|---|---|---|---|

| Opening WIP completed | 500 | 60% remaining | 300 |

| Started & completed (4,200 − 500) | 3,700 | 100% | 3,700 |

| Closing WIP | 300 | 50% | 150 |

| Total EU | | | 4,150 |

Step 2 — Cost per EU

= ₹1,05,000 ÷ 4,150 = ₹25.30 per EU (approx)

Step 3 — Cost of completed units

  • Opening WIP: ₹18,000 (b/f) + 300 EU × ₹25.30 = ₹18,000 + ₹7,590 = ₹25,590
  • Started & completed: 3,700 × ₹25.30 = ₹93,610
  • Total transferred out = ₹25,590 + ₹93,610 = ₹1,19,200

Step 4 — Closing WIP

= 150 EU × ₹25.30 = ₹3,795

Check: ₹18,000 + ₹1,05,000 = ₹1,23,000 ≈ ₹1,19,200 + ₹3,795 ✓ (small rounding difference acceptable)

---

Example 2 — Two cost elements (common exam pattern)

Ms. Iyer's chemical plant, Process 2, April 2026:

  • Opening WIP: 200 units, Materials 100% done, Conversion 30% done; cost b/f ₹12,000
  • Fresh input: 1,800 units; Completed: 1,700 units; Closing WIP: 300 units (Materials 100%, Conversion 40%)
  • Current costs: Materials ₹54,000; Conversion ₹42,000

Equivalent Units:

| | Materials | Conversion |

|---|---|---|

| Opening WIP (0% mat. left; 70% conv. left) | 0 | 140 |

| Started & completed (1,700 − 200 = 1,500) | 1,500 | 1,500 |

| Closing WIP | 300 | 120 |

| Total EU | 1,800 | 1,760 |

Cost per EU: Materials = ₹54,000 ÷ 1,800 = ₹30; Conversion = ₹42,000 ÷ 1,760 = ₹23.86

Opening WIP completion cost: 0 × ₹30 + 140 × ₹23.86 = ₹3,340

Total Opening WIP cost transferred: ₹12,000 + ₹3,340 = ₹15,340

Started & completed: 1,500 × (₹30 + ₹23.86) = 1,500 × ₹53.86 = ₹80,790

Closing WIP: 300 × ₹30 + 120 × ₹23.86 = ₹9,000 + ₹2,863 = ₹11,863

⚠️ Common exam mistakes

  • Don't include opening WIP costs when computing cost per EU. Under FIFO, only current period costs go in the numerator. Students often add ₹18,000 b/f to ₹1,05,000 — that's the Weighted Average method, not FIFO.
  • Don't use 100% for opening WIP equivalent units. Opening WIP was already partially done last period. You only account for the remaining work, e.g., if it's 40% done, use 60% in your EU calculation.
  • Don't forget to split the 'units completed' into two groups. FIFO requires you to treat 'opening WIP completed this period' and 'units started and fully completed this period' separately. Lumping them together loses marks.
  • Watch material completion percentage for closing WIP. Materials are often added at the start of the process (100% for any WIP), but conversion costs accumulate gradually. Don't apply the same % to both cost elements blindly — read the question.
  • Don't skip the reconciliation check. Always verify: Opening WIP cost + Current costs = Cost transferred out + Closing WIP cost. A ₹1–2 rounding difference is fine; a large gap means you've made an error in EU or cost assignment.
📖 Reference: FIFO Method — Institute of Chartered Accountants of India
Test yourself
Practice questions on this section, AI-graded with citations.
⚡ Practice now →