Worked Solution
✓ VerifiedNote on Missing Data: The question as stated does not provide the Total Contract Price (Contract Revenue). Without this figure, Contract Revenue to be recognised cannot be computed numerically. However, all steps of the methodology are demonstrated below, and the Percentage of Completion and Contract Cost to be recognised are fully computed from the given data.
Treatment of Advances under AS-7 (Accounting Standard 7 – Construction Contracts):
As per AS-7, when computing the stage of completion using the cost-to-cost method, costs incurred to date should relate only to work performed. Advances paid to sub-contractors represent a prepayment for future work and are excluded from the numerator of the percentage of completion formula.
Step 1 – Costs Incurred to Date (for work performed):
Only Sub-Contract Costs for work executed are considered = ₹7 Lakhs.
Advances paid to Sub-Contractors (₹4 Lakhs) are excluded as they do not reflect work performed.
Step 2 – Total Estimated Contract Cost:
Costs incurred to date (work performed): ₹7 Lakhs
Further costs estimated to complete: ₹35 Lakhs
Total Estimated Contract Cost = ₹7 + ₹35 = ₹42 Lakhs
Step 3 – Percentage of Completion:
Percentage of Completion = (Costs incurred for work performed ÷ Total Estimated Contract Cost) × 100
= (7 ÷ 42) × 100 = 16.67%
Step 4 – Contract Revenue to be Recognised:
As per AS-7, Contract Revenue to be recognised = Total Contract Price × Percentage of Completion.
Since the Total Contract Price is not provided in the question, let the Total Contract Price = ₹X Lakhs.
Contract Revenue to be recognised = ₹X × 16.67%
Step 5 – Contract Cost to be Recognised:
As per AS-7, Contract Costs to be recognised in the period = Total Estimated Cost × Percentage of Completion
= ₹42 Lakhs × 16.67% = ₹7 Lakhs
(This logically equals costs incurred for work performed to date, confirming internal consistency.)
Summary:
Percentage of Completion = 16.67%
Contract Cost recognised = ₹7 Lakhs
Contract Revenue recognised = 16.67% of Total Contract Price (requires contract price to compute).
Key Principle: Advances paid are excluded from the stage of completion calculation under AS-7, as including them would overstate the degree of completion and prematurely recognise revenue.
Write it like this
1The skeleton
- Lead with the AS-7 exclusion rule for advances — state upfront that advances paid to sub-contractors are excluded from costs incurred to date because they represent prepayment for future work, not work performed; examiners are specifically checking if you know THIS distinction.
- Build your cost table in two clear lines — Costs for work executed: ₹7L; Further costs to complete: ₹35L; Total Estimated Contract Cost: ₹42L — laying it out as a mini-table signals you know the formula inputs and grabs partial marks even if your percentage is wrong.
- Show the percentage formula explicitly — write '(Costs incurred for work performed ÷ Total Estimated Contract Cost) × 100 = (7 ÷ 42) × 100 = 16.67%' on its own line; examiners award a method mark here, so never skip the formula.
- Call out the missing contract price instead of leaving a blank — write 'Total Contract Price not given; let it be ₹X' and then express Revenue = 16.67% of X; this shows examiner you know the next step and protects you from losing the revenue recognition mark entirely.
- End with Contract Cost recognised = ₹7L and note the internal consistency — stating this equals costs incurred to date shows you understand the cost-to-cost method and closes the answer professionally, which late-checkers reward.
2Examiner-rewarded phrases
3Common trap
Heads up — almost everyone adds the ₹4L advance into the numerator (costs incurred = ₹11L) and gets 23.91%, which is wrong and kills 2-3 marks in one shot. AS-7 is crystal clear: only costs for work already executed go in the numerator, not prepayments.