💡 Show solution AI SOLUTION
Note on Missing Data: The question as stated does not provide the Total Contract Price (Contract Revenue). Without this figure, Contract Revenue to be recognised cannot be computed numerically. However, all steps of the methodology are demonstrated below, and the Percentage of Completion and Contract Cost to be recognised are fully computed from the given data.
Treatment of Advances under AS-7 (Accounting Standard 7 – Construction Contracts):
As per AS-7, when computing the stage of completion using the cost-to-cost method, costs incurred to date should relate only to work performed. Advances paid to sub-contractors represent a prepayment for future work and are excluded from the numerator of the percentage of completion formula.
Step 1 – Costs Incurred to Date (for work performed):
Only Sub-Contract Costs for work executed are considered = ₹7 Lakhs.
Advances paid to Sub-Contractors (₹4 Lakhs) are excluded as they do not reflect work performed.
Step 2 – Total Estimated Contract Cost:
Costs incurred to date (work performed): ₹7 Lakhs
Further costs estimated to complete: ₹35 Lakhs
Total Estimated Contract Cost = ₹7 + ₹35 = ₹42 Lakhs
Step 3 – Percentage of Completion:
Percentage of Completion = (Costs incurred for work performed ÷ Total Estimated Contract Cost) × 100
= (7 ÷ 42) × 100 = 16.67%
Step 4 – Contract Revenue to be Recognised:
As per AS-7, Contract Revenue to be recognised = Total Contract Price × Percentage of Completion.
Since the Total Contract Price is not provided in the question, let the Total Contract Price = ₹X Lakhs.
Contract Revenue to be recognised = ₹X × 16.67%
Step 5 – Contract Cost to be Recognised:
As per AS-7, Contract Costs to be recognised in the period = Total Estimated Cost × Percentage of Completion
= ₹42 Lakhs × 16.67% = ₹7 Lakhs
(This logically equals costs incurred for work performed to date, confirming internal consistency.)
Summary:
Percentage of Completion = 16.67%
Contract Cost recognised = ₹7 Lakhs
Contract Revenue recognised = 16.67% of Total Contract Price (requires contract price to compute).
Key Principle: Advances paid are excluded from the stage of completion calculation under AS-7, as including them would overstate the degree of completion and prematurely recognise revenue.