Launch offer — 25% off with code LAUNCH-25 See plans →
Microlesson · 5-min read

Features, Key Terms, Job vs Contract Costing, Cost Plus Contract, Escalation Clause, Sub-Contract

# Contract Costing

## Definition

A form of specific order costing where each contract is treated as a separate cost unit. Costs are accumulated and ascertained independently for each contract.

---

## Features of Contract Costing

  • A separate contract account is prepared for each contract
  • Contracts are usually large in scale, typically spanning more than one year
  • Work is executed at the site of the contract (not in the factory)
  • Only a small number of contracts are handled simultaneously
  • Two parties: Contractor (undertakes the work) and Contractee (awards the contract)

---

## Job Costing vs. Contract Costing

AspectJob CostingContract Costing
ScaleSmaller workLarge-scale work
LocationFactory premisesSite of contract
Indirect costsHigher proportionLower proportion
Number undertakenUsually manyUsually few
DurationShort-termOften > 1 year

---

## Key Terms and Formulae

TermMeaningFormula
Value of Work Certified (VOWC)Work completed and certified by contractee's architectContract Price × % certified
Progress Payment (PP)Payments received based on architect's certificateVOWC − Retention Money
Retention Money (RM)Security withheld by contracteeVOWC − Payment actually received
Cost of Work Uncertified (COWU)Cost of completed but uncertified workTotal cost to date − Cost of certified work
Notional ProfitProfit on the certified portionVOWC − Cost of Work Certified
Estimated ProfitTotal expected profit on the entire contractContract Price − Estimated total cost

---

## Cost Plus Contract (Contract Plus Costing)

Contract price = Total Actual Cost + Fixed % of Profit

When used: When estimating contract cost with reasonable accuracy is not possible (novel, complex, multi-year projects).

### Features

  • Suitable when contract completion will take several years
  • Contractee has the right to inspect the contractor's books
  • Aims for fair price to contractee and reasonable profit to contractor

### Advantages and Disadvantages

PartyAdvantagesDisadvantages
ContractorAssured fixed % profit — no loss risk; protected against cost escalationsCannot exploit favorable market conditions; no reward for cost efficiency; fear of cost objections
ContracteeCan verify actual costs via book access; gets benefit of cost decreases; price based on actuals not estimatesBears risk of contractor's inefficiency; may pay higher costs due to contractor's reduced incentive to control costs

---

## Escalation Clause

A contractual safeguard clause that revises the contract price upward if prices of materials or labour rise beyond a specified threshold. Protects the contractor from unforeseeable cost increases over a long contract period.

---

## Sub-Contract

When a contractor assigns a portion of the work to another party — the sub-contractor. The sub-contractor is accountable to the main contractor (not the contractee). Cost of sub-contract work is treated as a direct cost of the main contract.

---

## Profit Recognition on Incomplete Contracts

General principles:

Stage of CompletionProfit Credited
Less than 25%Nil — no profit recognized
25% to 50%1/3 × Notional Profit × Cash Ratio
50% to 90%2/3 × Notional Profit × Cash Ratio
Above 90%Reasonable estimated profit, adjusted for contingencies

Cash Ratio = Progress Payment ÷ Value of Work Certified

Worked example

### Example 1

Computing Key Contract Terms

Contract Price = ₹10,00,000 | Work certified = 60%

Payment received = ₹5,10,000 | Total cost to date = ₹5,80,000

Cost of certified work = ₹5,40,000

VOWC = 10,00,000 × 60% = ₹6,00,000

Retention Money = 6,00,000 − 5,10,000 = ₹90,000

Cost of Work Uncertified = 5,80,000 − 5,40,000 = ₹40,000

Notional Profit = 6,00,000 − 5,40,000 = ₹60,000

Estimated Total Cost = ₹9,00,000 (given)

Estimated Profit = 10,00,000 − 9,00,000 = ₹1,00,000

### Example 2

Profit Recognition at 60% Stage

Using data from the previous example:

Stage = 60% → apply 2/3 rule

Cash Ratio = 5,10,000 ÷ 6,00,000 = 0.85

Profit to credit = 2/3 × ₹60,000 × 0.85

= 2/3 × 51,000

= ₹34,000

This is a conservative recognition approach — profit is not taken until cash is actually received, protecting against bad debts.

⚠️ Common exam mistakes

  • Confusing Retention Money with Progress Payment — RM is the amount withheld (not received), PP is what is actually received
  • Using Total Cost to Date instead of Cost of Certified Work when calculating Notional Profit
  • Computing Notional Profit using contract price instead of VOWC
  • Classifying sub-contract cost as an indirect cost — it is a direct cost of the contract
  • Recognizing full profit on an incomplete contract irrespective of stage — profit recognition follows the graduated rule (1/3, 2/3, etc.)
  • Forgetting to apply the Cash Ratio in the profit recognition formula
Reference:
Now that you've read this — what's next?
Move from understanding → mastery in 3 clicks. Each option below picks up from this lesson's topic.
Start 15-min diagnostic