Launch offer — 25% off with code LAUNCH-25 See plans →
Microlesson · 5-min read

Issues in IRR — Mutually Exclusive Projects & Multiple IRR

## Issues in IRR

### A. IRR and Mutually Exclusive Projects

Mutually exclusive projects are those where selecting one precludes selecting the other (e.g., one plot of land usable for either Project S or Project L — choosing one rejects the other).

IRR can mislead with mutually exclusive projects because IRR is a percentage and ignores the scale of investment (the absolute quantum of money earned).

The core problem: A small project can show a high IRR yet add less to shareholder wealth than a larger project with a lower IRR. Choosing the high-IRR small project forgoes the extra NPV the larger project would have generated — reducing shareholders' wealth.

#### Why the conflict arises — reinvestment assumptions

  • NPV assumes interim cash flows are reinvested at the discount rate (logical, since all projects beating the discount rate are accepted).
  • IRR assumes reinvestment at the project's own IRR.
  • As a result, IRR favours projects with cash flows concentrated in early years over projects with larger later cash flows — even when the latter creates more wealth.

Resolution: Use NPV for the accept/reject ranking of mutually exclusive projects, or use MIRR, which removes the distorting reinvestment assumption.

> Caution: It is NOT safe to assume IRR is reliable even when the larger project also has the higher IRR — see Example 9, where Project A has both the larger investment and the higher IRR yet Project B is the wealth-maximizing choice at a 5% discount rate.

### B. Multiple IRR

When a project's cash flows change sign more than once during its life (a non-conventional cash flow pattern — e.g., outflow → inflows → a later major outflow), there can be more than one IRR.

Plotting discount rate (x-axis) against NPV (y-axis) gives a curve that crosses zero twice, producing two IRRs (IRR₁ and IRR₂).

Decision implication:

  • If the cost of capital is below both IRRs, a decision can still be made easily.
  • Otherwise the IRR rule becomes misleading: the project should be accepted only if the cost of capital lies between IRR₁ and IRR₂.

MIRR avoids the multiple-IRR problem entirely by collapsing all flows to a single terminal value.

Worked example

### Example 1

Example 8 — IRR ignores scale (mutually exclusive)

Year 0Year 1IRRNPV @ 10%
Project A(₹1,00,000)₹1,50,00050%₹36,360
Project B(₹5,00,000)₹6,25,00025%₹68,180

Project A's IRR (50%) beats B's (25%), but B's NPV is far higher. Since they are mutually exclusive, choosing A (because of IRR) sacrifices ₹68,180 − ₹36,360 = ₹31,820 of additional shareholder wealth. The larger project with the lower IRR maximises wealth. Decision: choose B (higher NPV).

### Example 2

Example 9 — even when the larger project has the higher IRR, NPV can disagree

YearProject A (₹)Project B (₹)
0(9,00,000)(8,00,000)
17,00,00062,500
26,00,0006,00,000
34,00,0006,00,000
450,0006,00,000

Project A has the larger investment AND the higher IRR: IRR(A) = 46%, IRR(B) = 35%.

But at a 5% discount rate, the NPVs reverse the ranking:

  • NPV(A) = ₹6,97,535
  • NPV(B) = ₹8,15,625

Project B has front-loaded less (its early cash flows are smaller), so it is penalised by IRR but rewarded by NPV. Decision: select Project B, despite its lower IRR — because IRR's reinvestment assumption overstates A. The anomaly is resolved by MIRR.

⚠️ Common exam mistakes

  • Always picking the higher-IRR project for mutually exclusive decisions — IRR ignores investment scale and can destroy wealth; use NPV.
  • Believing IRR is safe whenever the larger project also has the higher IRR — Example 9 shows it still can be wrong.
  • Not recognising non-conventional cash flows (more than one sign change) as the trigger for multiple IRRs.
  • With multiple IRRs, applying the simple 'accept if IRR > cost of capital' rule — the project is acceptable only when the cost of capital lies BETWEEN the two IRRs.
  • Confusing NPV's reinvestment-at-discount-rate assumption with IRR's reinvestment-at-IRR assumption — this difference is the source of the NPV/IRR conflict.
Reference:
Now that you've read this — what's next?
Move from understanding → mastery in 3 clicks. Each option below picks up from this lesson's topic.
Start 15-min diagnostic