Launch offer — 25% off with code LAUNCH-25 See plans →
Microlesson · 5-min read

Capacity Determination and Types of Capacity

## Capacity Determination

Capacity means the ability to produce. Different bases of measuring capacity exist depending on the purpose (planning, costing, control). Understanding the hierarchy of capacities is key to computing idle capacity and idle-time cost.

### Types of Capacity

Type of CapacityMeaning / Computation
Maximum / Theoretical / Installed / RatedThe full ceiling output assuming no stoppages. `Units per Hour × Hours per day × No. of days per year₹
Practical / AchievableRealistic capacity after deducting holidays, weekly offs and normal idle time. See computation below.
Normal / Average / ExpectedAverage of past actual capacity (smooths out seasonal/cyclical swings).
ActualCapacity actually used during the period.
Budgeted / EstimatedThe level set for the period; used to determine rates and for planning.
Idle CapacityCapacity not utilised — split into Normal and Abnormal (see below).
LicensedCapacity approved by an authority.

### Computing Practical Capacity

1. Working Days = Total Days − Holidays − Weekly offs

2. Practical Hours = (Practical Days × Hours per day) − Normal Idle Time

3. Practical Units = Practical Hours × Units per Hour

### Idle Capacity

  • Normal Idle Capacity = Maximum − Budgeted
  • Abnormal Idle Capacity = Budgeted − Actual

> Key idea: Normal idle capacity is the unavoidable gap between the theoretical ceiling and what we plan to do; abnormal idle capacity is the avoidable shortfall between what we planned (budgeted) and what we actually achieved.

Worked example

### Example 1

Computing Practical Capacity

A machine runs 8 hours/day, produces 50 units/hour. The year has 365 days, of which 52 are weekly offs and 13 are holidays. Normal idle time is 200 hours per year.

  • Working Days = 365 − 52 − 13 = 300 days
  • Practical Hours = (300 × 8) − 200 = 2,400 − 200 = 2,200 hours
  • Practical Units = 2,200 × 50 = 1,10,000 units

### Example 2

Idle Capacity Split

Maximum capacity = 1,20,000 units; Budgeted = 1,00,000 units; Actual = 90,000 units.

  • Normal Idle Capacity = 1,20,000 − 1,00,000 = 20,000 units
  • Abnormal Idle Capacity = 1,00,000 − 90,000 = 10,000 units

⚠️ Common exam mistakes

  • Confusing Normal idle capacity (Maximum − Budgeted) with Abnormal idle capacity (Budgeted − Actual).
  • Forgetting to deduct normal idle time when computing practical hours.
  • Using total days instead of working days (after removing holidays and weekly offs) for practical capacity.
  • Treating installed/rated capacity as achievable — it is the theoretical maximum, not what can realistically be produced.
Reference:
Now that you've read this — what's next?
Move from understanding → mastery in 3 clicks. Each option below picks up from this lesson's topic.
Start 15-min diagnostic