Launch offer — 25% off with code LAUNCH-25 See plans →
Microlesson · 5-min read

Internal Rate of Return (IRR) — Merits and Limitations

## Internal Rate of Return (IRR)

IRR is the discount rate at which NPV of the project equals zero—the break-even cost of capital.

> Solve for r in:

> Σ [CFt ÷ (1+r)^t] = Initial Outflow

Decision Rule:

  • IRR > WACC (Cost of Capital) → Accept
  • IRR < WACC → Reject

---

### Advantages

#Advantage
1Incorporates Time Value of Money
2Considers all cash flows throughout the project's life
3Intuitively comparable to cost of capital—managers immediately understand 'project earns 18% vs. 12% cost'
4Aligned with shareholder wealth maximisation objective

---

### Limitations

#LimitationDetail
1Tedious calculationRequires trial and error (interpolation) to find the rate; no closed-form solution for multi-period cases
2Misleading for unconventional cash flow patternsMultiple sign changes in cash flows can produce multiple IRRs
3Reinvestment rate assumption is unrealisticIRR assumes interim cash flows are reinvested at the IRR itself, which is usually not achievable
4Can conflict with NPV for mutually exclusive projectsIRR may rank a smaller-but-efficient project above a larger wealth-creating project

---

> IRR vs. NPV for mutually exclusive projects: When IRR and NPV rankings conflict, always follow NPV—it directly measures wealth addition. IRR is best used as a supplementary communication tool.

Worked example

### Example 1

A project costs ₹1,00,000 and generates ₹60,000 in Year 1 and ₹70,000 in Year 2. At 20%: PV = 60,000/1.2 + 70,000/1.44 = 50,000 + 48,611 = 98,611 (NPV = −1,389). At 18%: PV = 60,000/1.18 + 70,000/1.3924 = 50,847 + 50,273 = 1,01,120 (NPV = +1,120). IRR ≈ 18 + [1,120/(1,120+1,389)] × 2 = 18 + 0.89 ≈ 18.9%. If WACC = 12%, accept the project.

### Example 2

Project A: cost ₹1,00,000, NPV ₹20,000, IRR 25%. Project B: cost ₹5,00,000, NPV ₹80,000, IRR 20%. IRR favours A; NPV favours B. If mutually exclusive and the firm has sufficient funds, choose B—it adds ₹80,000 to wealth vs. ₹20,000. This conflict arises from scale difference, a known limitation of IRR.

⚠️ Common exam mistakes

  • Accepting a project simply because IRR is high without comparing it to WACC—the cost of capital is the correct hurdle, not an arbitrary threshold.
  • Using IRR to rank mutually exclusive projects without cross-checking with NPV—IRR rankings can mislead when project sizes differ.
  • Assuming there is always a unique IRR—projects with multiple cash flow sign changes (e.g., large decommissioning costs at end) can have multiple valid IRRs.
  • Confusing IRR's reinvestment assumption with NPV's—NPV implicitly assumes reinvestment at WACC (realistic); IRR assumes reinvestment at IRR (often unrealistic).
Reference:
Now that you've read this — what's next?
Move from understanding → mastery in 3 clicks. Each option below picks up from this lesson's topic.
Start 15-min diagnostic