# Blanket Rate vs Departmental Rate
## Blanket (Plant-wide / Factory-wide) Rate
A single overhead absorption rate for the entire factory.
$$\text{Blanket Rate} = \frac{\text{Total Overhead}}{\text{Total Base Quantity}}$$
Use when all products:
- pass through all departments, and
- are processed for the same time in each department, or
- there is only one product.
## Departmental Rate
A separate absorption rate for each production department, using the base appropriate to that department.
$$\text{Departmental Rate} = \frac{\text{Departmental Overhead}}{\text{Departmental Base Quantity}}$$
Use when products differ in the resources / time they consume across departments. More accurate (but costlier to operate).
## Quick comparison
| Blanket Rate | Departmental Rate | |
|---|---|---|
| Number of rates | One for whole factory | One per department |
| Accuracy | Lower (only valid in uniform cases) | Higher |
| Best fit | Single product / uniform processing | Mixed products with different resource use |