Quality Control Cost

# Quality Control Cost

## Definition

Quality Control Cost is the cost of all the resources used for quality control purposes.

## Key Points

  • It will be directly given in the question (you do not have to compute it).
  • It is added after Net Factory Cost and before arriving at Cost of Production.
  • It includes salaries of quality control staff, testing materials, depreciation of testing equipment, etc.

## Position in Cost Sheet

```

Net Factory Cost

+ Quality Control Cost

+ Research & Development Cost

+ Admin OH related to production

+ Primary Packaging

− Sale of scrap / by-product

= Cost of Production

```

Worked example

### Example 1

Example: If Net Factory Cost = ₹5,00,000, Quality Control Cost given in question = ₹25,000, R&D Cost = ₹15,000, and Primary Packaging = ₹10,000:

Cost of Production = 5,00,000 + 25,000 + 15,000 + 10,000 = ₹5,50,000

⚠️ Common exam mistakes

  • Trying to compute QC cost from items in the question — it is always given as a single figure.
  • Adding QC cost before factory cost (it comes after net factory cost).
  • Treating QC cost as admin OH.
Reference: