Launch offer — 25% off with code LAUNCH-25 See plans →
Microlesson · 5-min read

Economic Batch Quantity (EBQ) & Job vs Batch Costing

## Economic Batch Quantity (EBQ)

The lot/batch size is critical to achieving the least cost of operation. Total batch production cost has two opposing components:

1. Machine Set-Up Costs — incurred each time a batch is started.

2. Inventory Holding (Carrying) Costs — incurred for holding produced units.

### The trade-off

  • Larger batch → fewer set-ups → lower set-up cost, but more units in inventory → higher holding cost.
  • Smaller batchlower holding cost, but more set-ups → higher set-up cost.

EBQ is the batch size where the total of set-up + holding costs is minimum.

### Formula

$$EBQ = \sqrt{\dfrac{2DS}{C}}$$

Where:

  • D = Annual demand for the product
  • S = Setting-up cost per batch
  • C = Carrying cost per unit of production (p.a.)

(Note the structural similarity to EOQ — EBQ swaps ordering cost for set-up cost.)

---

## Difference Between Job Costing and Batch Costing

#Job CostingBatch Costing
1Used for non-standard, non-repetitive products made to customer specifications against specific orders.Used for homogeneous products produced in a continuous flow in lots.
2Cost determined for each job.Cost determined in aggregate for the whole batch, then reduced to a per-unit basis.
3Jobs are different, independent, and unique.Products in a batch are homogeneous and lack individuality.

Worked example

### Example 1

EBQ computation: Annual demand D = 40,000 units, set-up cost S = ₹100 per batch, carrying cost C = ₹0.50 per unit p.a.

EBQ = √(2 × 40,000 × 100 ÷ 0.50) = √(8,000,000 ÷ 0.50) = √16,000,000 = 4,000 units per batch.

⚠️ Common exam mistakes

  • Using ordering cost instead of set-up cost (S) in the EBQ formula.
  • Forgetting to take the square root, or mis-placing carrying cost C (it goes in the denominator).
  • Confusing annual demand with batch demand for D.
  • Using job costing logic (cost per job) for batch problems instead of aggregating then dividing per unit.
Reference:
Now that you've read this — what's next?
Move from understanding → mastery in 3 clicks. Each option below picks up from this lesson's topic.
Start 15-min diagnostic