Launch offer — 25% off with code LAUNCH-25 See plans →
Microlesson · 5-min read

PPE – Elements of Cost and Decommissioning

## PPE – Elements of Cost (AS 10 / Ind AS 16)

An item of Property, Plant and Equipment (PPE) that qualifies for recognition as an asset must be measured at cost.

### Three Elements of Cost

Element 1 – Purchase Price

  • Includes import duties and non-refundable purchase taxes.
  • Less: Trade discounts and rebates.

Element 2 – Directly Attributable Costs

  • Costs necessary to bring the asset to its working location and condition.
  • Examples: installation charges, freight, professional fees for site preparation.

Element 3 – Decommissioning / Restoration Costs

  • Initial estimate of costs to dismantle, remove, and restore the site.
  • These are known as decommissioning, restoration, and similar liabilities.
  • Obligation arises either at acquisition or due to usage during a period (other than to produce inventories).

### Decommissioning — Key Concept

When an old plant is dismantled to make way for a new plant at the same location, the dismantling cost is capitalised as part of the new PPE (not expensed).

> Rule: Costs of dismantling, removing, and restoring the site form part of the cost of the new asset.

### Auditor's Verification

  • Obtain cost sheet / capital work in progress schedule.
  • Verify each cost element against invoices and supporting documents.
  • Check whether decommissioning costs have been estimated and included.

Worked example

### Example 1

Scenario (JB Limited): JB Limited incurred ₹5,70,000 on dismantling an old obsolete plant so that a new plant could be set up at the same location. How should this be treated?

Answer: The ₹5,70,000 is a decommissioning cost (Element 3) and must be capitalised as part of the cost of the new plant, not charged to the P&L as an expense. This treatment follows AS 10 / Ind AS 16 — initial estimate of decommissioning costs forms part of the asset's cost.

### Example 2

Cost Classification Exercise: Classify the following for a new machine acquired:

  • Purchase price: ₹10,00,000 ✓ Element 1
  • Import duty: ₹50,000 ✓ Element 1
  • Trade discount received: (₹20,000) — deducted from Element 1
  • Freight to factory: ₹30,000 ✓ Element 2
  • Test run costs: ₹15,000 ✓ Element 2
  • Future dismantling estimate: ₹25,000 ✓ Element 3
  • Total capitalised cost: ₹11,00,000

⚠️ Common exam mistakes

  • Treating dismantling costs as revenue expenditure (P&L charge) instead of capitalising them as part of the new asset cost.
  • Including refundable taxes in the purchase price — only non-refundable taxes are capitalised.
  • Forgetting to deduct trade discounts and rebates from the purchase price.
  • Confusing decommissioning costs with routine maintenance costs — routine maintenance is always revenue expenditure.
Reference:
Now that you've read this — what's next?
Move from understanding → mastery in 3 clicks. Each option below picks up from this lesson's topic.
Start 15-min diagnostic