Launch offer — 25% off with code LAUNCH-25 See plans →
Microlesson · 5-min read

AS 16 – Period of Capitalisation: Commencement, Suspension, and Cessation

## AS 16 – When to Start, Pause, and Stop Capitalising

Capitalisation of borrowing costs does not automatically run from loan disbursement to asset completion. AS 16 specifies three control points.

---

## A. Commencement of Capitalisation

Capitalisation begins only when ALL three conditions are simultaneously satisfied:

ConditionDetail
1. Expenditure incurredMoney has actually been spent on the QA
2. Activities in progressWork necessary to prepare the asset has started — includes both physical work AND technical/administrative work (e.g., registration, site preparation, planning, permits)
3. Borrowing cost being incurredInterest is actually running on the loan

> Common trap: Physical construction is not required to start capitalisation. Technical work like registration, planning, and site preparation also qualifies as "necessary activities."

---

## B. Suspension of Capitalisation

Capitalisation must be suspended during extended periods when active development is NOT taking place.

Exception – Do NOT suspend if the interruption is:

  • A temporary delay that is a normal and necessary part of the construction process
  • e.g., seasonal shutdowns, curing periods, mandatory inspection delays

### Example:

```

Construction start: 01.04.Y1

Strike (work stops): 01.11.Y1 – 30.11.Y1

Construction end: 31.12.Y1 (total 24 months planned)

→ Strike = extended inactive period → SUSPEND capitalisation for November

Contrast:

Bridge construction where river floods for 2 months = normal part of process

→ Do NOT suspend (temporary delay, part of normal process)

```

---

## C. Cessation of Capitalisation

Capitalisation ceases when substantially all activities necessary to prepare the QA for its intended use or sale are complete.

Key points:

  • Minor pending work (e.g., decoration, minor finishing) does not delay cessation
  • The test is "substantially complete," not "100% complete"

### Completion in Parts (e.g., multi-tower project)

When a QA is completed in separable parts:

  • Stop capitalising on each part as soon as it is complete and can be used independently
  • Continue capitalising on remaining parts still under construction

```

Example: Apartment complex with Tower A and Tower B

→ Tower A complete and habitable: STOP capitalising on Tower A

→ Tower B still under construction: CONTINUE capitalising on Tower B

```

---

## Summary Timeline

```

[Loan disbursed]

[All 3 conditions met] ← START capitalising

[Extended inactivity?] ← SUSPEND (unless normal process delay)

[Activity resumes] ← RESUME capitalising

[Substantially complete] ← STOP capitalising (each separable part)

```

Worked example

### Example 1

Example – Commencement with Technical Work

Timeline:

  • 01.04.Y1 – Loan disbursed, expenditure incurred
  • 01.05.Y1 – Borrowing cost begins
  • 01.06.Y1 – Registration and planning work begins
  • 01.07.Y1 – Physical construction begins

Q: When does capitalisation commence?

A: 01.06.Y1 — All three conditions are met on this date:

1. Expenditure incurred (01.04) ✓

2. Borrowing cost incurred (01.05) ✓

3. Necessary activities started — registration/planning on 01.06 counts ✓

Physical work starting on 01.07 is NOT the commencement date because condition 3 was already satisfied in June.

### Example 2

Example – Suspension due to Strike

  • Construction start: 01.04.Y1
  • Strike: 01.11.Y1 to 30.11.Y1 (one month, extended inactivity)
  • Construction end: 31.12.Y1

Total cap months = April–October (7m) + December (1m) = 8 months

November is suspended.

Contrast: If a bridge construction stops during monsoon season as expected/planned, this is a normal part of the process → No suspension.

### Example 3

Example – Phased Completion

Total loan = ₹2,00,00,000 @ 15% → Annual interest = ₹30,00,000

Project has 4 phases:

  • Phases I & II: Cost = ₹98 lakhs, completed (ready for use) at 6 months
  • Phases III & IV: Cost = ₹1,23 lakhs, still under construction at year-end

Interest for Phases I & II = 30,00,000 × (proportionate) = ₹13,30,317 (12 months)

  • During 6-month cap period: ₹6,65,159 → Capitalise
  • Remaining 6 months (after ready): ₹6,65,159 → Charge to P&L (asset ready; stop capitalising)

Interest for Phases III & IV = ₹16,69,683

  • Work still in progress → Capitalise (₹16,69,683)

Total BC Capitalised = 6,65,159 + 16,69,683 = ₹23,34,842

Total BC to P&L = ₹6,65,159

⚠️ Common exam mistakes

  • Starting capitalisation from the date of loan disbursement — capitalisation only begins when ALL three conditions (expenditure, activities, borrowing cost) are simultaneously satisfied.
  • Requiring physical construction to begin before capitalisation can start — technical and administrative work like registration, planning, and permits also satisfy the 'activities' condition.
  • Suspending capitalisation for every work stoppage — only extended periods of genuine inactivity require suspension; normal/temporary process delays do not.
  • Continuing to capitalise after an asset (or part of it) is substantially complete — once substantially all activities are done, stop capitalising even if minor finishing work remains.
  • Treating a multi-part QA as a single asset for cessation purposes — each separable, usable part triggers cessation independently when that part is ready.
Bare-Act text Paragraphs 17, 20, and 22 · AS 16 – Borrowing Costs · click to expand
Capitalisation of borrowing costs should commence when: (a) expenditure for the acquisition, construction or production of a qualifying asset is being incurred; (b) borrowing costs are being incurred; and (c) activities that are necessary to prepare the asset for its intended use or sale are in progress. Capitalisation of borrowing costs should be suspended during extended periods in which active development is interrupted. Capitalisation of borrowing costs should cease when substantially all the activities necessary to prepare the qualifying asset for its intended use or sale are complete.
Now that you've read this — what's next?
Move from understanding → mastery in 3 clicks. Each option below picks up from this lesson's topic.
Start 15-min diagnostic